Look Organized and Still Produce Surprises

Decisions missing. Consequences coming. Assumptions already escalating. — Unsigned approval document with eyeglasses and a pen on a desk.

The schedule is issued and the meetings are running. The decisions guiding the work may still have no owner.

A project can look organized while nobody owns its core decisions. Assumptions fill the gap, design and pricing build on them, and the cost surfaces later as change orders. Before design advances, name who owns each core decision, when it has to be made, and what work can proceed until it is.

Consider a headquarters renovation.

The monthly report looked fine. The schedule had been issued. Design was progressing on time. The estimate had been updated, the weekly meetings were well attended, and the action-item list was getting shorter.

Then the 50 percent design estimate came in well over budget, and the conversation turned to why.

Nobody had made a bad decision. Several important decisions had never been made at all. Whether the café would stay in the program. Whether the existing air handlers would be reused. How many floors would remain occupied during construction. Each question had been raised. Each had been carried forward to the next meeting. In the meantime, the design team had drawn something, because drawings have to show something, and the estimators had priced what was drawn.

The project looked organized because it was organized. What it lacked was someone with the authority to close those questions before the work built on top of them.

What Fills the Gap When Nobody Decides?

When decisions are missing, projects substitute for them.

Assumptions replace decisions. A placeholder for the café becomes the basis of the layout, and after a few months of drawings it carries the weight of an approved requirement.

Momentum replaces direction. The schedule says design development ends in March, so design development ends in March, whether or not the questions it depended on were answered.

Participation replaces accountability. Everyone who might have an opinion is invited to the meeting, the discussion is thorough, and the item is carried to next week because nobody in the room can close it.

Why the Cost Shows Up Later

None of this looks like a problem while it is happening. Design keeps advancing, estimators keep pricing, and the schedule keeps moving.

Each of those activities is building on assumptions rather than decisions. When leadership finally weighs in on the café, the air handlers or the phasing, the drawings, the estimate and sometimes the procurement already reflect a different answer.

Changing course at that point means redesign, repricing and, if construction has started, change orders. What should have been a leadership decision months earlier arrives as a contractor’s request for additional money, and it gets handled as a transaction instead of the decision it always was.

More Meetings Won’t Close the Gap

When surprises start appearing, the usual response is more structure: more meetings, more reporting, more coordination.

The project was never short on activity. It was short on someone authorized to decide. Adding meetings gives open questions more places to be discussed and still no place to be closed. It can even make things worse, because a busier process looks more under control.

What Do Strong Capital Programs Do Differently?

Strong programs separate making decisions from producing work. Before design advances, pricing hardens or schedules commit, they establish three things for each core decision:

Who owns it
When it has to be made
What work can proceed until it is

The list doesn’t need to be long. On most projects, a handful of decisions drive scope, cost and schedule: program elements, reuse or replacement of major systems, phasing and occupancy, quality level, and budget authority. Naming an owner and a date for each one turns open questions into a schedule of decisions, and it tells the design team which assumptions are safe to build on.

That is what governance means on a capital project: sequencing decisions ahead of the work that depends on them.

The Warning Signs 

Projects with unclear decision ownership look busy, responsive and on schedule. Watch for these instead:

The same open item appears in the meeting minutes three weeks in a row.
The answer to “Who decided that?” is “It was in the drawings.”
The estimate moves, and nobody can point to the decision that moved it.
People describe a requirement as “the plan” without being able to say who approved it.

Any one of those means the project is building on an assumption. Several together mean the assumptions are running the project.

Before the Next Project Review

The best-performing capital programs are the ones where the important decisions are visible, owned and made on time, however busy they look.

At your next project review, ask one question before anyone opens the schedule:

Which decisions are still open, and who owns each one?

If nobody can answer, the project may look organized. It isn’t being governed yet.


About the Author: Richard Neuman is an independent owner’s representative for office build-outs, ground-up construction, relocations, and capital programs in New York City and Long Island. He has overseen more than $2 billion in capital investments across commercial real estate, healthcare, utilities, industrial, broadcast, and development projects.

He writes Straight Talk on Capital Projects, a candid owner-side look at the executive decisions and organizational dynamics that shape capital project outcomes.

Planning a renovation, relocation, or new building, or leading a major capital program? Talk through your project with Richard.

Subscribe for insights on capital planning, project governance, and the executive decisions that shape project outcomes long before construction begins.

Be the first to comment on "Look Organized and Still Produce Surprises"

Leave a comment

Your email address will not be published.


*

Found this article useful? Share it with a colleague.